Karanlıkdere Balanced Cantilever Viaduct
Construction of a 286-metre, three-span balanced-cantilever viaduct on the Kastamonu-Çankırı (Kırık Dam Variant) road.
Field Engineering on a Balanced-Cantilever System
Constructed within the scope of the Kastamonu-Çankırı (Kırık Dam Variant) road, the Karanlıkdere viaduct is a three-span bridge structure built with the balanced-cantilever method. With a total length of 286 metres, the production, assembly and on-site fabrication are carried out by FTK Group as subcontractor under the employer partnership of Cengiz İnşaat & HGG İnşaat.
The total scope includes 26,239 m³ of concrete and 5,977 tonnes of reinforcement-steel works. The planned schedule is 18 months and works are progressing rapidly under disciplined site management.
Numbers That Define the Project
- 286m
Total viaduct length
- 26,239m³
Concrete works
- 5,977tons
Reinforcement steel
- 3spans
Number of spans
Balanced-Cantilever System and Site Discipline
- 01
Balanced-Cantilever Method
The balanced-cantilever construction method was selected to suit span characteristics; structural balance is maintained through symmetric advance from the support axis.
- 02
High-Volume Concrete & Steel
26,239 m³ of concrete and 5,977 tons of reinforcement steel are managed with site logistics and laboratory follow-up.
- 03
18-Month Schedule Discipline
The 18-month planned schedule is sustained through disciplined site planning of timeline and resources.
Other References

Direcik & Kozalaklı Viaducts
End-to-end construction of two major viaducts on the Aydın-Denizli Motorway; delivered with 101,455 m³ of concrete and 20,000 tons of rebar.

Akhisar Stormwater Line
Central urban stormwater drainage built with a precast box-culvert system in the centre of Manisa Akhisar.

V01 Viaduct
Construction of a 700-metre main-line viaduct on the Ankara-Kırıkkale-Delice Motorway, advancing toward year-end delivery.